How to compare provisional sums in builders’ quotes

A provisional sum is an allowance for work the builder cannot yet price precisely. Two builders can allow very different amounts for the same item, so the lower total can give you the wrong impression.

Compare the same drainage allowance

Imagine two quotes for the same extension. Both include drainage, but the route to the existing drain still needs checking. Read the allowances already included in each total before you add anything.

Illustrative extension quotes
What you compareBuilder ABuilder B
Price quoted£48,000£50,000
Drainage allowance included£1,000£4,000
Total using £4,000 for both£51,000£50,000

For Builder A, subtract the £1,000 already included and add £4,000. Builder B’s figure stays the same. The £4,000 is just a common assumption for this comparison. Ask both builders to price the actual route once it’s known.

What to ask each builder

Check that both figures treat VAT and any builder’s markup consistently. Keep the written replies alongside the quotes so you can see which costs still need a decision.

Compare your own quotes

Get the free ten-question checklist to use with both builders. For a comparison sheet and wording you can send them, see the £250 video lesson and toolkit.