How to compare provisional sums in builders’ quotes
A provisional sum is an allowance for work the builder cannot yet price precisely. Two builders can allow very different amounts for the same item, so the lower total can give you the wrong impression.
Compare the same drainage allowance
Imagine two quotes for the same extension. Both include drainage, but the route to the existing drain still needs checking. Read the allowances already included in each total before you add anything.
| What you compare | Builder A | Builder B |
|---|---|---|
| Price quoted | £48,000 | £50,000 |
| Drainage allowance included | £1,000 | £4,000 |
| Total using £4,000 for both | £51,000 | £50,000 |
For Builder A, subtract the £1,000 already included and add £4,000. Builder B’s figure stays the same. The £4,000 is just a common assumption for this comparison. Ask both builders to price the actual route once it’s known.
What to ask each builder
- What length, depth and access have you assumed for the drain?
- Does the allowance cover excavation, removal of spoil, pipework and making good?
- What information would let you give a firm price, and when will I receive it?
- How will you calculate and agree any adjustment before the work goes ahead?
Check that both figures treat VAT and any builder’s markup consistently. Keep the written replies alongside the quotes so you can see which costs still need a decision.